Add following material in an SAP BOM item

Following BOM item missing

After a BOM copy or migration to a new plant, the following items might not have been copied.

For example, for Material M :
Material M / Plant A / BOM X
Initial material : item 010, material 1 valid to 01.09.2015
Following material : item 010, material 2 valid from 01.09.2015 with a change number, is not copied for Material M in Plant B (Fig 1)

SAP CS03 Display material BOM: General Item Overview - BOM containing an item with a following component
Fig 1 : SAP CS03 Display material BOM: General Item Overview – BOM containing an item with a following component

Copied to (2 cases) :

First case : Material M / Plant B / BOM Y
Initial material : item 010, material 1 valid to 31.12.9999
Following material 2 missing (Fig 2.1)

SAP CS03 Display material BOM: General Item Overview - BOM copied with item following component missing
Fig 2.1 : SAP CS03 Display material BOM: General Item Overview – BOM copied with item following component missing

Second case : Material M / Plant B / BOM Y
– Initial material 1 missing
Following material : item 010, material 2 valid to 31.12.9999 (Fig 2.2)

SAP CS03 Display material BOM: General Item Overview - BOM copied with initial item component missing
Fig 2.2 : SAP CS03 Display material BOM: General Item Overview – BOM copied with initial item component missing

In this case, the BOM X in Plant A must have a change number associated to the following material.

There are then 2 different cases, see in CS03 – Display material BOM : General Item Overview which one applies by comparing BOMs in Plant A and Plant B for Material M.

1 – Initial material copied, following material can be added

First case, the material copied in Plant B is the initial material, actually used – you can then jump to step 3.

2 – Following material was copied, change it to initial material and add following material

In case the following material was copied, you have to perform an extra step.

First of all, enter Material M and Plant B in CS02 – Change Material BOM: Initial Screen (Fig 3) (no need to change the Valid From date), put the initial material in place of the following material in CS02 – Change Material BOM: General Item Overview (Fig 4), and saveicon.

SAP CS02 Change material BOM: Initial Screen - Enter material and plant to update items
Fig 3 : SAP CS02 Change material BOM: Initial Screen – Enter material and plant to update items
SAP CS02 Change material BOM: General Item Overview - Update item material
Fig 4 : SAP CS02 Change material BOM: General Item Overview – Update item material

3 – Add following material

After you have ensured the initial material is present, you can add the following material. Enter in CS02 the Material M, Plant B, and change number (Fig 5).

SAP CS02 Change material BOM: Initial Screen - Enter material, plant and change number
Fig 5 : SAP CS02 Change material BOM: Initial Screen – Enter material, plant and change number

After entering a description for the change (Fig 6), the change number will automatically populate the Valid from date with the change number date (Fig 7), which is the one you want to use.

SAP CS02 Change material BOM: Object Management Data - Enter a change description
Fig 6 : SAP CS02 Change material BOM: Object Management Data – Enter a change description
SAP CS02 Change material BOM: Initial Screen - Date automatically copied from change number
Fig 7 : SAP CS02 Change material BOM: Initial Screen – Date automatically copied from change number

You can then put the item following material in place of the initial material (Fig 8), and saveicon.

SAP CS02 Change material BOM: General Item Overview - Update item with following component and change number
Fig 8 : SAP CS02 Change material BOM: General Item Overview – Update item with following component and change number

4 – Check setup

Double check afterwards in CS03 that the final configuration corresponds to what you want – Plant B / BOM Y with an active material and a following material starting at a given change number date (Fig 9).

SAP CS03 Display material BOM: General Item Overview - Target BOM updated
Fig 9 : SAP CS03 Display material BOM: General Item Overview – Target BOM updated