Cost center does not exist KI265

The message KI265 cost center does not exist can be solved by either selecting a correct cost center, or by creating a cost center for the required period corresponding to the purchase order being created for example.

This SAP FICO error might happen in SAP S4HANA and R3 versions of the SAP ERO.

Cost center XXXX does not exist on 15.09.2010.
Cost Center does not exist

Cost center does not exist : Cost center does not exist error during purchase order creation
Cost center does not exist error during purchase order creation

The error KI265 is the following:

DIAGNOSIS: Cost center in controlling area does not exist or only exists in the period prior to.

PROCEDURE: Enter an existing cost center.

Alternately, create cost center for the period you require. In this case you must create the document again after creating the cost center. If you wish you can temporarily store the document and then continue processing it after creating the cost center.

KI265 – COST CENTER &/& DOES NOT EXIST – KI 265

Cost center does not exist : Cost center does not exist message number KI265
Cost center does not exist message number KI265

Create cost center in SAP

If it is necessary to create a cost center in SAP to solve the error KI265 cost center does not exist, and to proceed with a purchase order creation, it might be that a corresponding cost center already exists, but is not valid for the dates in which the PO is being created.

Start by opening the create cost center tcode KS01.

Cost center does not exist : Transaction code KS01 create cost center
Transaction code KS01 create cost center

In the create cost center in SAP transaction KS01, start by entering the controlling area, the cost center code, and most importantly, the valid from date and valid to date, which must cover at least the date range of the goods processing.

Cost center does not exist : Create cost center transaction KS01 initial screen
Create cost center transaction KS01 initial screen

The controlling area cannot be selected directly in the create cost center initial screen, but has to be accessed from the menu extras > set controlling area, or by using the keyboard shortcut F6 set controlling area.

Cost center does not exist : Set controlling area menu in KS01 create cost center
Set controlling area menu in KS01 create cost center

In the set controlling area pop-up, it is possible to select the right controlling area to use, and, if necessary, to use the SAP help to find the right controlling area that will be useful to create the cost center for the correct date range.

Cost center does not exist : Selection of controlling area for cost center creation
Selection of controlling area for cost center creation

Cost center accounting in SAP

Once the right controlling area has been selected, the cost center code has been entered, and the date range of the cost center to create have been entered, it is possible to proceed with the cost center creation, to have it available for SAP accounting.

Cost center does not exist : Creation of a cost center for a given date range
Creation of a cost center for a given date range

In the create cost center basic screen, the main information to enter are the following:

  • name, to quickly identify the cost center corresponding to the given code,

  • description, to give more information about the cost center usage,

  • person responsible, a text field with the name of a collaborator that will be able to answer of this cost center,

  • the cost center category, which indicates the type of cost center it is, for example production, administration, or sales and distribution,

  • hierarchy area, a tree structure with all profit centers belonging to a given controlling area,

  • currency, in which currency payments are made for this cost center, and how it will be reported.

    Cost center does not exist : Create cost center transaction KS01 basic screen

Create cost center transaction KS01 basic screen

Once all these information have been entered, it is possible to save the cost center.

If information is correct, the cost center creation will proceed, and if date range is large enough, it will now be possible to proceed with the purchase order creation.

Cost center does not exist : Cost center created in KS01 transaction
Cost center created in KS01 transaction

How to check cost center in SAP

SAP cost center tables

  • CSKS cost center master data,

  • CSKT cost center texts,

  • CRCO assignment of work center to cost center,

  • CSSL cost center and activity type,

  • CSSK cost center and cost element.

SAP cost center tables

SAP cost center transactions

  • KS03 display cost center,

  • KS01 create cost center,

  • KS04 delete cost center,

  • KS02 change cost center,

  • KKC3 display cost object,

  • KA03 display cost element.

SAP Display Cost Center Tcodes (Transaction Codes)